# A Value Date in the Wrong Century

Industry: Finance

### A Value Date in the Wrong Century

A ten-year swap leg settles on a value date sent as 350615. The receiving system stores a date.

The usual approach:
```js
// The naive approach: a cut-off of 30 that someone chose, stated through the pattern parser
import { parseDateWithPattern } from "@northguild/gmt/plain/parse";

parseDateWithPattern("350615", "yyMMdd", undefined, { yearWindow: 1930 });
// "1935-06-15" — a century before the settlement date
parseDateWithPattern("750615", "yyMMdd", undefined, { yearWindow: 1930 });
// "1975-06-15" — accepted, and SWIFT refuses it
```

SWIFT states the century for a value date. It reads a two-digit year from 01 to 60 as 2001 to 2060, and refuses any other with error code T50. So 350615 is 15 June 2035. The cut-off above puts it in 1935, a century before the date the payment settles.

The same cut-off accepts 750615 as 1975. SWIFT refuses that value, because 75 is not a year from 01 to 60. So the check passes the bad data and the system stores a date nobody sent.

The cut-off is a choice someone made, not a rule SWIFT states. parseSwiftDate applies SWIFT's own rule, so there is no choice left to get wrong.

With GMT:
```js
import { parseSwiftDate } from "@northguild/gmt/finance/parse";
import { isValidSwiftDate } from "@northguild/gmt/finance/validate";

parseSwiftDate("350615"); // "2035-06-15"
parseSwiftDate("750615"); // ""
isValidSwiftDate("750615"); // false
```

To see the same value in the tool, [open `350615` in the SWIFT Value Date
Reader](/gmt/tools/swift-value-date-reader/?w=swiftdate&wa=%7B%22value%22%3A%22350615%22%7D). The full
rule is in [Finance: Message Timestamps](/gmt/guides/industries/finance-message-timestamps/).