Add business days
addBusinessDays moves a date forward by working days. With no calendar it counts Monday to Friday.
import { addBusinessDays } from "@northguild/gmt/plain/calculate";
addBusinessDays("2024-03-15", 1); // "2024-03-18"2024-03-15 is a Friday, so the next working day is Monday 2024-03-18.
A weekend that is not Saturday and Sunday
Section titled “A weekend that is not Saturday and Sunday”Pass the weekend as ISO weekday numbers (Monday is 1, Sunday is 7), the holidays as dates, and the time zone. Saudi Arabia in Asia/Riyadh has its weekend on Friday and Saturday, so [5, 6].
import { addBusinessDays } from "@northguild/gmt/plain/calculate";
addBusinessDays("2024-07-04", 1, { weekend: [5, 6], holidays: [], timeZone: "Asia/Riyadh",}); // "2024-07-07"2024-07-04 is a Thursday. Friday 07-05 and Saturday 07-06 are weekend days, so the answer is Sunday 2024-07-07.
Temporal’s PlainDate has no working-day operation, so this is a function you call on the string, not a method on a value. The result is a date string again.
Holidays come from you
Section titled “Holidays come from you”GMT holds no holiday list. You pass the dates your organisation treats as non-working, in the format YYYY-MM-DD.
import { nextBusinessDay } from "@northguild/gmt/calendar/business";
nextBusinessDay("2024-03-15", { weekend: [6, 7], holidays: ["2024-03-18"], timeZone: "Africa/Nairobi",}); // "2024-03-19"Monday 2024-03-18 is in the list, so the next working day after Friday is Tuesday 2024-03-19.
Count working days between two dates
Section titled “Count working days between two dates”import { businessDaysBetween } from "@northguild/gmt/calendar/business";
businessDaysBetween("2024-03-15", "2024-03-22", { weekend: [6, 7], holidays: [], timeZone: "Europe/Berlin",}); // 5What to expect
Section titled “What to expect”| Call | Input | Result |
|---|---|---|
addBusinessDays(value, 1) | Friday 2024-03-15 | "2024-03-18" |
addBusinessDays(value, 1, calendar) | Thursday 2024-07-04, weekend [5, 6] | "2024-07-07" |
nextBusinessDay(value, calendar) | Friday 2024-03-15, holiday 2024-03-18 | "2024-03-19" |
businessDaysBetween(start, end, calendar) | 2024-03-15 to 2024-03-22 | 5 |
addBusinessDays(value, 0) | Saturday 2024-03-16 | "2024-03-16" |
An amount of 0 returns the input unchanged, even when it falls on a non-working day. Use rollDate to move a non-working day onto a working one.
Checked on 2026-10-26 with GMT 1.20.0.
See also: addBusinessDays, nextBusinessDay, businessDaysBetween, rollDate. Migrate from date-fns lists the fixed-weekend addBusinessDays there.